TYPE
Extension/Refurbishment
VALUE
£1.53m
DURATION
36 weeks
CLIENT/ARCHITECT
Coda Workshops LTD
QS
Greenwood Projects Ltd
BSN delivered a youth community project under the Government’s Youth Improvement Fund (YiF) Framework by overcoming initial budget challenges.
Through competitive tendering and value engineering workshops—optimizing design, materials, and removing mezzanine floors—the team aligned the scheme with the revised £950k budget after securing additional funding, ensuring both cost control and quality delivery.
Project Status
Completed
in association with
BSN successfully completed the youth community project under the YiF Framework, meeting the March 2025 funding deadline despite budget constraints, complex site conditions, and design challenges.
Strategic value engineering, collaborative redesign, and accelerated programming ensured all variations and technical issues were resolved, delivering a compliant, high-quality facility within the revised scope and budget.