TYPE
Refurbishment
VALUE
£3.2m
DURATION
40 WEEKS
CLIENT/ARCHITECT
GILLING DOD
QS
WT PARTNERSHIP
The full refurbishment is part of a wider refurbishment programme of works which we are involved with at BCHC NHS Trust.
The facility had been cleared and stripped out by a previous contractor, therefore, this project was a relatively easy fitting out scheme. However, unforeseen internal drainage issues and client changes extended the original swift 20 week programme.